The Facilities Department plans, designs, builds and maintains OCPS buildings to provide students with safe, comfortable, updated facilities for successful learning.
Our team is proud to include about 400 employees in Maintenance, Grounds and Pest Control and about 1,200 workers in Custodial Services.
To learn how new schools are planned, look at our fact sheet or watch our informational video series. For building program updates, visit Building Schools.



Project Manager for CFO

Toni Greene
407-317-3700 ext. 2025930

Media and Public Information:

Facilities Communications
Lauren Roth
407-317-3700 ext. 2023774


Close up shot of John Morris
Chief Facilities Officer
John Morris

News Releases

OCPS to hold Sneak Peeks for new schools 07.31.20

Three new OCPS elementary schools named by community 04.14.20

Site 80-H-SW-4 Groundbreaking 03.02.20

Previous News Releases

Community Meeting Notices

Site 113-H-W-4 40% Construction Community Meeting 08.17.20

Site 80-H-SW-4 40% Construction Community Meeting 08.12.20 

Edgewater HS Field Lighting Community Meeting 07.27.20

Orange Technical College - Orlando 60% Design Community Meeting 07.23.20

Site 132-M-W-4 60% Design Community Meeting 07.22.20

Site 43-E-SE-2 100% Design/Construction Kickoff Community Meeting 07.20.20

Site 90-K8-N-7 60% Design Community Meeting 07.16.20

Edgewater HS Field Lighting Meeting 07.07.20

Site 113-H-W-4 Groundbreaking Invitation 04.09.20

Previous Community Meeting Notices


Community Meeting Presentations

Orange Technical College - Orlando 60% Design Community Meeting Presentation 07.23.20

Site 132-M-W-4 60% Design Community Meeting Presentation 07.28.20

Site 43-E-SE-2 100% Design/Construction Kick-off Community Meeting Presentation 07.20.20

Site 90-K8-N-7 60% Design Community Meeting Presentation 07.16.20

Edgewater HS Field Lighting Presentation 07.27.20

Winegard ES 40% Construction Community Meeting Presentation 03.09.20

Site 85-E-W-4 40% Construction Community Meeting Presentation 03.04.20

Pinar Elementary 40% Construction Community Meeting Presentation 02.26.20

Site 83-E-SE-3 40% Construction Community Meeting Presentation 02.24.20

Site 20-E-SW-4 40% Construction Community Meeting Presentation 02.20.20

Magnolia School 40% Construction Community Meeting Presentation 02.06.20

Jones HS Capital Renewal Community Meeting Presentation 01.27.20

Site 43-E-SE-2 30% Design Community Meeting Presentation 01.16.20

Site 73-T-W-7 30% Design Community Meeting Presentation 01.16.20

Rolling Hills Elementary 40% Construction Community Meeting Presentation 01.15.20